The system is now flushed, so now you need to calibrate the valves.

1. Adjust all valves throughout the system. Start at the pump and work towards the end of the system. At each point, adjust the valves to match the pressure indicated on the design.

 

 

2. Close the laterals or, if using a flushing manifold, close the valves of the flushing manifold.

 

 
 

Explore the next module, or search for a specific topic or issue.

Before using the content of the Knowledge Hub, please familiarize yourself with the relevant disclaimers and additional safety and usage information contained within the modules/guides being viewed. Keep in mind that due to numerous variances for every application, before making any product or application decision, as always, you should consult with a local irrigation consultant for your specific needs. Case study outcomes are for informational purposes only and actual results may vary.

© 2026, Rivulis Irrigation Ltd, all rights reserved. 
Reproduction of this content in any form is prohibited without the written consent of Rivulis Irrigation Ltd.